We are rebuilding Trinity Academy in two phases. When both phases are complete the school will have space for 1,200 pupils.
Phase 1
Phase 1 of the project involved the construction of a new sports building at the Bangholm Recreational Grounds which opened in 2022. The centre provides excellent new PE facilities for the school as well as improvements to the existing playing fields. The building features a
- four-court sports hall
- gym hall
- dance studio
- fitness suite
- classroom
- changing facilities.
Outside retains the grass pitch and a refurbished 2G sand dressed pitch.
The facilities are designed to meet the curricular and extra-curricular requirements of Trinity Academy. It also supports local hockey and rugby clubs and local primary schools.
Phase 2
Phase 2 of the project is to build a new school building and refurbish the Victorian building.
The construction programme started in 2024 and will run for three school sessions until August 2028. The construction phasing plan is:
- initial demolition and enabling work (this started Spring 2024)
- construction of on-site temporary decant accommodation (completed Octoiber 2024)
- demolition of remaining buildings (completed July 2025)
- construction of the new school building
- landscaping
- Victorian building refurbishment.