Murrayburn Gate - construction of 73 new affordable homes

Murrayburn Gate - delivery of 73 new affordable homes

Architectural drawing of the new development at Murrayburn gate

Project Overview

Murrayburn Gate is delivering 73 high-quality, energy-efficient affordable homes for the City of Edinburgh Council, helping meet housing need in the west of Edinburgh.

The development will provide a mix of 41 social rent and 32 mid-market rent homes, designed to modern energy efficiency standards with attractive landscaped communal spaces.

Latest Update – July 2026

The project has reached an important milestone with the first homes approaching handover in August 2026

The initial phase of 12 new social rent homes has been completed, and new residents are anticipated to move into the development later in August 2026 . Construction and finishing work continue across the remaining homes, with further handovers planned over the next two months.

Overall completion remains on programme for late September 2026.

Progress at a Glance

Status

Progress

Construction

Substantially complete

First homes

Handover has started

Remaining homes

Internal finishes and commissioning underway

External works

Continuing across the site

Landscaping

In progress

Overall completion

September 2026

Creating Sustainable Homes

  • High-quality energy-efficient homes
  • Modern insulation and building fabric
  • Attractive landscaped open spaces
  • New play area for residents

Benefits for the Community

  • 73 new affordable homes
  • A mix of social and mid-market rent accommodation
  • New landscaped green spaces
  • High-quality homes supporting Edinburgh's housing needs

What's next?

Work will continue on the remaining homes, communal areas and landscaping before the development is completed towards the end of September 2026. Further homes will be handed over in phases as they are completed and ready for occupation.

Local access and safety

Traffic plan and working schedules continue to minimise disruption. Local access to the shopping plaza remains.

Controlled pedestrian routes remain in place until all work is complete.

Planning history

  • 4 July 2022 – Planning permission for 73 affordable housing units with associated infrastructure and landscape. (ref: 22/03302/FUL)

  • 28 August 2024 – Non material variation application (ref: 22/03302/FUL). Changes proposed to turning head in accordance with CEC roads request for RCC application.